Balance of plant (BOP) term usually used in the field of Power Engineer which is refer all the supporting components, machinery and auxiliary power system of the Power plant which is essential for power generation.
Balance of plant the following
important components:
Raw water intake
Fuel
supply
Air
intake
Cerray
Boiler
Raw water intake
Raw water is done both from canal and well.
Priority is given to canal water in this plant because it contains less TDS
(Total dissolved salts). Though canal water contains more TSS (Total suspended
solids) and turbidity, but since removing TDS is more expensive, we prefer
canal water here. But for back up, well water can be taken as well. Following
steps are taken to purify water:
1. Trash Rack
It is used to remove solids, debris, wood pieces, biological growth, and
dead animals etcetera.
Trash Rack
Here, suspended particles are removed from water through the rotating
screens which are also back washed though raw water.
Travelling Band Screen
3. Clarifier Raw
water
pumps pump the water into clarifier where different dosing is done. Here
coagulant and hypo dosing are done. Sodium Hypochlorite is used for hypo dosing
and Al2(SO4)3 is used as
a
coagulant which converts smaller
particles into bigger particles which can be used thorough Eliminators. To
speed up the process, coagulant aid (Polyacrylamide) is used.
Clarifier Raw
4. UGNO1
The
filtered enters UGNO1 which is a storage pit.
5: Pressure filter Pressure
Filters
are also used for filtration and here sand, gravel and anthracite do the
filtration.
Filter Pressure
Water then enters UGNO2 which is a filtered water
basin. At this point, water’s TSS and and turbidity has been removed.
7. Two bed
To remove salts and dissolved
salts, there are many methods, like using softeners, remove osmosis and
distillation but we use ion exchange method here. Here we use a cation
exchanger which is a resin on which are Hydrogen ions followed by a Degasifier
and then an anion exchanger which is a resin which has hydroxide ions.
Degasifier has a blower which removes gases. After this method, conductivity
becomes around 2us/cm.
8. Mixed Bed
Here there are cation and ion
exchange resins and remaining conductivity is removed which comes around
0.1us/cm. From here, water goes to demineralization tank.
9. Regeneration
Cation and anion exchangers (resins) are
regenerated though sulphuric acid and sodium hydroxide respectively.
Regeneration