In
the USA 789 billion kWh energy produced by 100 nuclear reactors in 2015.
Its to hard to control the atomic fusion reaction but in this process o lot of heat emits. By using this heat we will able to produce Electricity. the complete phenomena show in above GIF.
Its to hard to control the atomic fusion reaction but in this process o lot of heat emits. By using this heat we will able to produce Electricity. the complete phenomena show in above GIF.
In simple language when an atom of
Uranium 92 break and heat produced and the water cross from there.
When water crosses the reactor part turn into vapor. We use
these vapors to turn the generator shaft to get required RPM.
In the atomic plant temperature very high.So
it is necessary to cool down the Plant area except for the reactor part.
Without cooling the Plant its impossible to Work there. So cooling the plant
water is used and mostly all the Atomic power plant located near the river
side to fill full the requirements of water to cool down and vaporization
to produce energy. Its a very expensive and dangerous source of
electricity. with a single mistake, you become the victim of harm
full radiation which effect your body badly. Always
use high-level protection when you are working in the Nuclear power
plant.
One Kg Atom of Uranium 92 can
produce Electricity equal to 30 Ton Coal. Its to interesting to
hear but it has more complication then coal power plants.
One of the most important things is
the Security issues. the atomic material is mush sensitive material
and no good in bad hands. The government pays there full
attention for the security by using there secretes agencies
and well-trained commando.
Watts Bar 2 Power Plant
It
was started in 1985 but due to some manger issues stopped when its
completed 80% and 1996 1 unit start working. After that resumed this work at
2007 and expected to gain 116 MW electricity from this reactor at
2012 to 2013 but in vain. At that time forecast, the expected cost was
$2.5 billion. The project was not completed at this cost and
postponed to 2016 at the budget of $4.7 billion
Vogtle
3&4 Power Plant.
This
project was singed in April 2008 and expected to complete in 2019 or
2020. Two Westinghouse AP1000 reactor of 1200 MW project
was singed with two companies one of them was Westinghouse
and the other one is The Shaw Group in April 2008 by Georgia Power.
In 2012 February NCR gives him the COL and in
the staring due to concrete problem postponed from 2012 to March
2013.After a lot of problems finally, Construction of unit 3 was
started in March 2013 and unit 4 was in November.
14 billion dollar
cost was forecast at the staring but due to again late in the
center of 2014 cost increased 381 million dollar.When the
other delay declared in January 2015 the expertise of said that the cost
of per month increase $40 million in which $10 million escalation cost and $30
million was financing cost.In 2014 $6.5 billion dollar loan was issued by
Georgia Power & Oglethorpe and remaining $1.8 billion of the loan was
issued by 3 partners Municipal Electric Authority of Georgia
(MEAG) as guarantees in 2015 June.
Hanul
Nuclear Power Plant (formerly, Urchin)
Hanul Nuclear Power
Plant is situated in South Korea Located in Gyeongsangbuk-do province and the
largest in South Korea. Firstly it’s known
as Urchin Nuclear Power plant and renamed Hanul Nuclear Power
Plant in 2013.
According to the output
Hanul Nuclear Power Plant is at 4th number among Nuclear power plants. The net
capacity is 5908 MW and the installed gross generation of electricity is
6189MW.
Hanul
Nuclear Power Plant divided into 2 units. The first unit was
completed in 2005. Total six PWR( Pressurized water reactor) used in phase 1
and 2 more water reactor was used in next development of phase 2. The expected
completion of phase 2 is 2018, by adding two more reactors the net
capacity will be 8608 and the 1350MW capacity of each new reactors. The power
plant gross capacity will be 8989MW in 2018.Shin-Ulchin 1 and 2 units
Power Plant
In July 2012 working in
Shin-Ulchin stared with the estimated capital of $6bn. In the
Shin-Ulchin unit 1 APR 1400 PWR used with the net capacity of 1340 MW. The unit
was operational in 2105.
The construction of Shin-Ulchin unit 2 started in September 2013 and will be finished in 2018. The net capacity is 1340 with using APR 1400 Pressure water reactor.
The construction of Shin-Ulchin unit 2 started in September 2013 and will be finished in 2018. The net capacity is 1340 with using APR 1400 Pressure water reactor.
Ulchin nuclear power
plant reactors
The unit 1 & 2 of
Hanul Nuclear Power Plant based on the CPI model of FRANCE. Its unit 1& 2
used APR 1400 which is known as Korean Technology Reactor.
Ulchin
nuclear Power Plant upgrade
Till September 2002
Ulchin power plant used as thermal Power plant and after that thermal
reactor was upgraded for Hanul Nuclear Power Plant unit 1 & 2.
After the update, the net capacity of electricity increase 54MW, firstly
1003MW to 1057MW. A long-term policy was required to
enhance the capability of the plant, decrease the maintenance cost and safety
of the nuclear material.
Safety measures implemented at Ulchin NPP
Safety is
first preference and more concentrate using different equipment.
· Injection
system (SIS).
· The
safety depressurisation system (SDS).
· Emergency feed-water system.
· Containment
spray system.
Bruce
Power Generating Station, Toronto, Canada
Bruce Power Generating
plant in short BPGS is the second position among of largest Nuclear Power
plants. It is located in near the lake Huron about 250
km northwest of Toronto Ontario Canada. It is the first non-govt
power plant and the largest plant in North America and 2nd largest in the
whole world because of the first one Kashiwazaki-Kariwa.
Ontario Hydro started construction of BPGS in 1970 and the construction was complete at 1987 approximate in 17 years. BPGS produced 20 % electricity of Ontario which is very interesting. BPGS has the total area about 2,300- acre. BPGS divided in two part first one is called Bruce A and the second One is called Bruce B. Due to some issues Bruce A were out of form and all the reactors were shut down between 1995 - 1998 but during this period Bruce B working very well. In January 2004 and October 2003 respectively the remaining 3rd and 4th unit of Bruce A was resumed. When all the rector working there full potential then the net generation of electricity around 6,232 MW.
Ontario Hydro started construction of BPGS in 1970 and the construction was complete at 1987 approximate in 17 years. BPGS produced 20 % electricity of Ontario which is very interesting. BPGS has the total area about 2,300- acre. BPGS divided in two part first one is called Bruce A and the second One is called Bruce B. Due to some issues Bruce A were out of form and all the reactors were shut down between 1995 - 1998 but during this period Bruce B working very well. In January 2004 and October 2003 respectively the remaining 3rd and 4th unit of Bruce A was resumed. When all the rector working there full potential then the net generation of electricity around 6,232 MW.
Bruce Power Plant
History
In 1987 all the
construction work and the installation was completed by Ontario Hydro
the division of time such as the 1st two units was starting working
in 1977 and the second one are completer in 1978-87, Bruce B was completed
and generated electricity in 1982-87.in 1999 Ontario Power generation
(OPG) also added in Ontario Hydro and total Ontario divide in 5 parts. OPG
operate all the power generating plant in the Canada.
BPGS Plant details
CANDU is the name of
reactors which is used in Bruce A and Bruce B in a heavy safety building and
using the specific material to control the radiation effect and rate of
reaction.
Total 8 number of
reactor installed in the Bruce A and 6 are working normally but the two
the reaming 2 are under construction those can produce 1500
MW and now rated capacity is 4700MW.
Kashiwazaki-Kariwa
Nuclear Power Plant
Kashiwazaki Karina plant is the world largest Power
plant in the earth it is situated in Tokyo (Japan) under the hold of
TEPCO Tokyo Electric Power Company. TEPCO fulfill the electricity demand
of 16 million house-holds. Kashiwazaki Karina is the 4th one
largest nuclear plant due to its 7965 MW net capacity.
The first 3 are given below.
1. Itaipu near Brazil-Paraguay border.
2. Three Gorges Dam in China.
3. Guri Dam in Venezuela.
The total install capacity is 8,212MW by using 7 BWR ( boiling
water reactor ).Kashiwazaki Karina becomes the first Power plant
which is using the Advanced Boiling water reactor made by General Electric.
ABWR used in reactor number 3 and produced 1315MW and the gross capacity was
1356MW.
Gross capacity of all 7 BWR are different 1st five has
1,100MW but the next 2 are 1,356.
Approximately after 12 years of hard work in
Kashiwazaki Karina plant, all the unit start working. The first unit
start in September 1985 and the last unit began commercially work in July 1997.
The plant was working in 1985 but due to safety check and problems of an
earthquake, the plant was re-opened in 2009.
Nuclear power plant safety is one of most important thing so
TEPCO starts working on the suggestion about the safety which
was given by Japan’s Nuclear Regulatory Authority.
The Japan face a no. Of earth quake, in each year so
every building which is design in Japan according to absorb the
maximum earth quake shock. The plant building also well safe but
the earth quake of 2007 measuring 6.8 on Richter scale was
damaged the Power Plant so due to earth quake the radioactive
substance and radiation escaped cause the badly effect the water and
air.
2007
earthquake damage
In 2004 October the earthquake measured 6.8 hit the
Niigata Prefecture city and effected the daily life.
Kashiwazaki Karina plant works normally
during the earth quake but the single one unites try to
force shutdown.
Grand Coulee Dam has
capacity of 6,809 MW
It is one of the
widest Energy plants in the whole United state. It
can produce 20 billion kWh/year. It becomes 5
no. After the 4 nuclear power plants. Which is little behind
Palo verde is the has capacity 3747 MW and can produce 30
billion kWh per year.
Palo
verde Power Plant
Palo verde is the has capacity
3747 MW and can produce 30 billion kWh per year.Palo Verde
Nuclear give 98% capacity factor In 2014 and run 24 hours in 7 days.
Salem
3 Power Plant
At the Hope creek, Nj wants
to install two modest Salem reactor and send application
form PSEG. They give the green signal at
the environmental condition so good. This project is
in waiting for 2016 list and a green signal was given in 2015.
Thanks for Suggestion
EmoticonEmoticon